From the past researches and projects it is noted that the delays of construction projects are categorized into number of types such as critical or non critical, excusable or non excusable, concurrent or non concurrent and compensable or non compensable.
CRITICAL OR NON CRITICAL DELAY
Critical delay is originated by some construction delays by which the project can’t complete within a specific period of time or on target date. Non critical delay is that the construction delays which affect the project development stage but not affect on specified target date.
EXCUSABLE OR NON EXCUSABLE
Excusable delays are executed by unpredictable circumstances on a construction project such as heavy rain, fire, policy changes, delay by client and many more. Non excusable delays are caused within the control of the executer or contractor. Delays such as sub contract delay, not completing project on specified time period, additional or faulty construction and many more are some non excusable delays.
COMPENSABLE OR NON COMPENSABLE
The delays that are excusable are likely to be compensable. In most cases extension of time period and in some cases time extension inclusive of an extra payment are considered for compensation. But the delays are compensable or not are considered by depending on the signed contract bond between the client and contractor. Non compensable delays are the delays caused irrespective to contractor and client. Natural disasters, bad weather conditions some examples for non compensable delays. But in some cases if client agrees extension of time period is given as compensation.
CONCURRENT OR NON CONCURRENT
Concurrent delay is caused by two or more delays happened at same time or their occurrence time overlap and finally affect the project schedule. In some cases the concurrent delays are compensable whether extensions of time period or liquidated damage claim.
Internationally and nationally the construction industry plays a major role in the development of economy. But the term delay in the respective field questioning the overall output of the industry. From the past researches and also from my survey it is noted some factors plays a role in contributing the term delay in the field of construction industry. The given below are some factors of example. Delays from consultant side, client side, contractor side, delay in design or other approvals from government organization, delays from lack of equipment, material, labour and other resources, delays from external environment, unpredictable weather conditions, natural disasters, delays from poor site management, manpower failures, specialness of project, poor communication, site conditions, lack of financial forecast and many more factors that are lead to delay of construction projects nationally and internationally. Finally, the identification of factors that causes delay on a construction project and identification of the type of delay at the proper stage could minimize the damage or effect caused from project delays. Also the proper safeguard plans at the right time will help to rectify the effects from the delays in building construction projects.